This record tracks Oppidan Edge Data Center - Beaver Dam in Wisconsin.
Beaver Dam published details for a proposed 90,000-square-foot edge data center by Oppidan at Highway 151 and Hemlock Road, adjacent to Generac; the city fact sheet lists an estimated $40M minimum taxable value, up to 16 MW of energy use, about 6,000 gallons per day of water use, 15 full-time jobs, and no requested TIF incentive. Daily Dodge reported the Common Council approved the second Beaver Dam data center on April 6, 2026, including sale of slightly more than 14 acres for $407,340.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-19. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.