OpenAI Stargate - Saline Township Campus
Sponsors & Partners
Project Timeline
Current canonical record
575-acre campus at US-12 & Braun Road. Five buildings including three large data halls, generator facility, warehouse, and administrative office. Later 2026 financing and construction announcements describe the Oracle/Stargate campus as a US$16 billion project.
Sources in the Feb-Jun 2026 window report state air and wetland permits issued in January 2026, financing secured at $16 billion, and a June 1, 2026 groundbreaking/shovel ceremony for the 2.2 million sq ft campus. Planet Detroit reported the January permits allow destruction of about 9 acres of wetlands and installation of 15 diesel backup generators; Michigan Public reported the June 1 groundbreaking.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-19. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.