549 acres total: 391-acre parcel rezoned February 2025, additional 158 acres approved later. Campus with 5 buildings planned.
AES Indiana's April 23, 2026 filing-related reporting identifies Google as the customer for the proposed Morgan County data center near Monrovia and states that the power agreement covers a 390 MW project, with Google paying the full cost of powering it and related energy projects. The $1.3 billion in the source is a power-supply cost estimate, not a replacement for the tracked project investment.