Canceled

MillCompute Bates Mill AI Data Center

Maine — Lewiston , Androscoggin County
Mega-Project
$300M
Investment
24 MW
Power Capacity
3
Sponsors

Sponsors & Partners

Project Timeline

Announced
2025-12-16

Current canonical record

This record tracks MillCompute Bates Mill AI Data Center in Maine.

A proposed $300 million AI data center inside Lewiston's downtown Bates Mill was released publicly six days before a pivotal December 2025 vote and was unanimously voted down by the City Council. The Maine Monitor reported on April 6, 2026 that the rejected proposal previewed broader Maine data-center debates; the Bates Mill project would have employed about 30 workers, according to city estimates.

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.