Canceled
Midwest Power Investors - Rochelle Steward Road Data Center
Illinois — Rochelle , Ogle County
Mega-Project
48 MW
Power Capacity
2
Sponsors
Sponsors & Partners
Midwest Power Investors LLC
LFF Industrial
Project Timeline
Announced
2026-02-11
Current canonical record
This record tracks Midwest Power Investors - Rochelle Steward Road Data Center in Illinois.
Shaw Local reported that Rochelle City Council voted unanimously on April 27, 2026 to deny the development agreement for a proposed 300,000-square-foot data center north of Steward Road, west of the BNSF railroad and south of Interstate 88; the first phase would have required 48 MW, with optional later phases to 100 MW and beyond 150 MW.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-17. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.