Project Timeline
Announced
2025-02
Construction Start
2025-11
Expected Completion
2027
Current canonical record
More than 500-acre site at Beaver Dam Commerce Park
Wisconsin regulators approved the Alliant-Meta individual power contract in May 2026; amended filings disclosed a 10-year supply arrangement for 220 MW, materially above the prior 143 MW estimate. Wisconsin Watch's May 2026 report described construction as ongoing at the Beaver Dam Commerce Park site.