Operational
Mass General Brigham Enterprise Data Center (Marlborough)
Massachusetts — Marlborough , Middlesex County
Mega-Project
$35M
Investment
5.2 MW
Power Capacity
1
Sponsors
Sponsors & Partners
Mass General Brigham (formerly Partners Healthcare)
Project Timeline
Announced
2012-05-16
Construction Start
2011
Current canonical record
This record tracks Mass General Brigham Enterprise Data Center (Marlborough) in Massachusetts.
Located at 555 Forest St. Developed with Leggat McCall Properties providing feasibility, due diligence, design and construction leadership. Designed to Tier III+ standard. Supports enterprise data ecosystem for Mass General Brigham hospital network.; Investment estimated at $7M/MW
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.