Planned

Lightedge - Ames Aviation Way Edge Colocation Facility

Iowa — Ames , Story
Mega-Project
25 MW
Power Capacity
1
Sponsors

Sponsors & Partners

Project Timeline

Announced
2026-06-18

Current canonical record

This record tracks Lightedge - Ames Aviation Way Edge Colocation Facility in Iowa.

Lightedge proposed leasing roughly 10.86 acres of city airport land on Aviation Way, west of Sigler Companies, for a phased edge colocation data center. City materials describe phase one at 3 MW, phase two at 6 MW, and ultimate buildout of 25 MW over about 10 years. Council review and public listening sessions were underway; no final approval was reported.

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-17. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.