Expansion
Keel Scrubgrass AI/HPC Data Center Campus
Pennsylvania — Kennerdell / Scrubgrass Township , Venango County
Mega-Project
1.3 GW
Power Capacity
1
Sponsors
Sponsors & Partners
Keel Infrastructure (formerly Bitfarms)
Project Timeline
Announced
2026-07-02
Current canonical record
This record tracks Keel Scrubgrass AI/HPC Data Center Campus in Pennsylvania.
DCD describes Scrubgrass as Keel's largest Pennsylvania project and its 'crown jewel.' Keel is targeting a 750 MW grid connection plus 550 MW of natural-gas capacity, roughly 1.3 GW total, at the former Stronghold/Bitfarms waste-coal and crypto-mining site as part of a pivot from crypto mining toward AI and high-performance computing data centers.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-17. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.