Mega-Project
$150M
Investment
16 MW
Power Capacity
1
Sponsors
Sponsors & Partners
Iron Mountain
Project Timeline
Announced
2024
Construction Start
2025-02-26
Expected Completion
2026
Current canonical record
Located on 3.4-acre site at 2925 NW 120th Terrace
Groundbreaking ceremony held February 26, 2025. Topped out in August 2025. First Iron Mountain data center in Miami. AI-ready facility with high-density GPU support.; Investment estimated at $7M/MW
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.