Planned

Hilcorp Endicott Bitcoin Mining Pilot

Alaska — Prudhoe Bay , North Slope Borough
Mega-Project
2
Sponsors

Sponsors & Partners

Project Timeline

Announced
2024-11
Construction Start
2024-11
Expected Completion
2028-11

Current canonical record

Small pilot data center in shipping container for Bitcoin mining

Pilot project to demonstrate feasibility of operating data center infrastructure in North Slope environment. Uses natural gas to power Bitcoin mining in shipping container on gravel pad at Endicott oil field. Could earn approximately $300/hour from mining operations. Permit under review by Alaska Department of Natural Resources.; QA 2026-07-19: Retained 1.4 MW only as computing load and cleared modeled investment.

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-19. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.