Mega-Project
$6.0B
Investment
407 MW
Power Capacity
1
Sponsors
Sponsors & Partners
Google
Project Timeline
Announced
2007
Expected Completion
2025
Current canonical record
Multiple expansions: $1B (2024), $600M (2022), $350M (2023). Total investment of $6.8B+ since 2007
Google's largest data center campus, located on southern edge of Council Bluffs along I-29. This is the fourth expansion since initial construction in 2007. $1.3M pledged for Missouri River valley water preservation and conservation.; B+ total; 3M sq ft; 407 MW MidAmerican renewable wind; multi-phase since 2009
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.