Mega-Project
$1.0B
Investment
100 MW
Power Capacity
3
Sponsors
Sponsors & Partners
Thor Equities
Form8tion
JDS Equities II LLC
Project Timeline
Announced
2025
Current canonical record
810-acre campus between Hitchingham Rd & Milan-Oakville Rd. 522.2 acres requiring rezoning. Uses 1 million gallons of water per day.
Township Board of Trustees unanimously approved rezoning in July. However, Protect Augusta Charter Township (PACT) collected 957 signatures (561 needed) to trigger referendum for 2026 ballot. Faces significant local opposition. Would use 20% of 800-acre site. Thor Equities founded Form8tion in March 2023 as data center development unit.; Power estimated at $7M/MW