Mega-Project
30 MW
Power Capacity
2
Sponsors
Sponsors & Partners
Enerfore Digital Valley, LLC
Enerfore Digital
Project Timeline
Announced
2024-10-01
Current canonical record
This record tracks Enerfore Digital Pleasant Valley Data Center in North Dakota.
Williams County planning materials dated 2025-01-16 describe the Pleasant Valley Data Center as a proposed 30 MW blockchain data center on a 10-acre site in Williams County, with a power ESA executed, land purchased, and fiber confirmed. KFYR reported on 2025-02-18 that the Enerfore Digital Data Center had received a conditional use permit earlier that month and that Teton Digital's Project Trinity would be located next to it.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.