Under Construction

Google Project Tembo (formerly Crusoe/Tallgrass Project Jade)

Wyoming — Cheyenne , Laramie County
Mega-Project Southeast Wyoming
$50B (reported)
Investment
1.8 GW (2.7 GW configuration, scalable to 10 GW)
Power Capacity
716 acres
Total Area
3
Sponsors

Sponsors & Partners

Project Timeline

Announced
2025-07-24
Construction Start
2026-01
Expected Completion
2031

Google Project Tembo (formerly Crusoe/Tallgrass Project Jade)

Google is the confirmed owner behind Wyoming’s largest data center build. A June 30, 2026 site-plan amendment filed with Laramie County — not a company announcement — revealed that Google, acting through subsidiary Jupiter Star Holdings, LLC, owns and will operate the campus formerly known as Project Jade, now renamed Project Tembo. At full scale it would use roughly five times more electricity than all homes in Wyoming combined.

Key Metrics

MetricValue
Investment$50B (reported project scale)
Power Capacity2.7 GW (first phase 1.8 GW; scalable to 10 GW)
Campus716 acres, Switchgrass Industrial Park
LocationCheyenne, Laramie County, Wyoming
RegionSoutheast Wyoming
StatusUnder Construction
Planned Completion2031

Stakeholders

Owner / Operator

  • Google (via subsidiary Jupiter Star Holdings, LLC) — disclosed June 30, 2026

Power & Infrastructure Partners

  • Tallgrass Energy (dedicated generation, Cheyenne Power Hub)
  • Black Hills Energy (grid capacity, 230 kV substation, Large Power Contract Service Tariff)

Former Developer

  • Crusoe Energy Systems (replaced as builder/operator by Jupiter Star Holdings in June 2026; construction continued through the transition)

Purpose

This project is designed for:

  • AI / ML
  • Hyperscale

Power Sourcing

Tallgrass Energy blends Black Hills Energy grid capacity, fuel cells, and its own generation, delivered to the campus through a dedicated substation. Despite earlier “bring-your-own-power” positioning, the project is grid-tied rather than fully off-grid. Site plans describe on-site wastewater treatment with evaporative lagoon storage after a connection to Cheyenne’s municipal system was deemed not cost-effective.

Campus

The 716-acre campus, about 8 miles south of Cheyenne on land formerly used for seasonal cattle grazing, includes four data center halls, an office hub, logistics and network buildings, and new access roads off U.S. 85. A further 32.83-acre office support parcel entered permitting in July 2026, with a Laramie County Commission hearing set for August 13, 2026.

Timeline

MilestoneDate
Announced (Crusoe/Tallgrass, 1.8 GW scalable to 10 GW)2025-07-24
Laramie County site-plan approval (Project Jade)2026-01-06
Crusoe replaced by Google subsidiary Jupiter Star Holdings2026-06
Google ownership revealed via county site-plan amendment2026-06-30
Office support parcel hearing2026-08-13
First-phase utility service target (Black Hills)Early 2028
Planned completion2031

Phases

  • Phase 1: Initial 1.8 GW capacity (first service targeted early 2028)
  • Full campus: 2.7 GW configuration by 2031
  • Long-term: Scalable to 10 GW