Planned

CoreWeave Lancaster County AI Data Center

Pennsylvania — Lancaster , Lancaster County
Mega-Project
$6.0B
Investment
3
Sponsors

Sponsors & Partners

Project Timeline

Announced
2025-07-15
Construction Start
2025
Expected Completion
2027

Current canonical record

Initial 100MW IT capacity scalable to 300MW. Former LSC Communications/R.R. Donnelley printing plants. 144 acres with 1.5 million sq ft industrial space.

Sites at 216 Greenfield Road and 1375 Harrisburg Pike. 600 jobs during construction, 70 FTE at launch scaling to 175. Announced at Pennsylvania Energy and Innovation Summit. May be largest single investment in Lancaster County history.; QA 2026-07-18: Retained the disclosed 100 MW in IT load and cleared the duplicate facility-power value.

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-18. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.