Mega-Project
$100M
Investment
100 MW
Power Capacity
1
Sponsors
Sponsors & Partners
Core Scientific
Project Timeline
Announced
2021-05
Construction Start
2021
Expected Completion
2021-11
Current canonical record
20 acres site at 5601 11th Ave S
Sixth mining and colocation hosting facility for Core Scientific. Secured $269,000 loan from Grand Forks Growth Fund. Partnership with Nodak Electric Cooperative and Minnkota Power Cooperative. Originally designed to support nearly 3 exahash of computational power. Created up to 12 highly skilled technical jobs. Access to major fiber routes between Minneapolis, Fargo, and Winnipeg.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.