Operational

Cologix Lakeland Data Center

Florida — Lakeland , Polk County
Mega-Project
$70M
Investment
10 MW
Power Capacity
1
Sponsors

Sponsors & Partners

Current canonical record

100,000+ square feet of data center space at 2850 Interstate Drive, Lakeland, FL 33805. Acquired from Colo5 with land for expansion

Purpose-built in 2013, located centrally between Tampa and Orlando with easy access to Interstate 4 and two major international airports. Robust fiber network optimized for performance and speed. Acquisition accelerated Cologix's Florida expansion plans by 18 months. Cologix operates more than 225k SF of colocation space in Florida.; Power estimated at 100 W/sqft from 105,000 sqft; investment at M/MW

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.