Canceled

CleanSpark New Salem Bitcoin Mine

Tennessee — Unknown , Washington County
Mega-Project
25 MW
Power Capacity
3
Sponsors

Sponsors & Partners

Current canonical record

This record tracks CleanSpark New Salem Bitcoin Mine in Tennessee.

Data Center Dynamics reported on April 8, 2026 that CleanSpark shut down the 25 MW Bailey Bridge Road Bitcoin mining facility near the New Salem community after a court settlement required operations to cease by March 28, 2026 and equipment to be removed within 120 days. The site came under CleanSpark control through its October 2024 acquisition of GRIID Infrastructure.

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-17. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.