This record tracks AWS Clinton Data Center Project in Mississippi.
MDA announced on April 9, 2026 that Amazon's latest Mississippi investment includes a planned $1 billion Clinton project creating 100 jobs and retrofitting the former Delphi Corporation plant. Mississippi Today reported on June 9, 2026 that Amazon said the Clinton facility is in the site-prep and pre-construction phase. Status remains planned because the company characterized the phase as pre-construction rather than active vertical construction.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-17. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.