This record tracks AWS Calvert Cliffs Data Center Campus in Maryland.
Calvert County says AWS submitted initial application documents for the Calvert Technology Center site plan on May 4, 2026, paid application fees on May 18, paid Environmental Health fees on May 26, and the application was formally accepted for processing on May 27, 2026. Departments and reviewing agencies completed first-round Concept Site Plan review and sent comments to AWS on July 13, 2026; the next step is for AWS to resubmit a revised Concept Site Plan. No project-specific MW or investment amount was identified.
Record provenance