Planned

Atlas Agro Richland Data Center Campus

Washington — Richland , Benton County
Mega-Project
$500M
Investment
350 MW
Power Capacity
1
Sponsors

Sponsors & Partners

Project Timeline

Announced
2025-12-02

Current canonical record

This record tracks Atlas Agro Richland Data Center Campus in Washington.

Tri-Cities Area Journal of Business reported on 2026-07-13 that Richland's city council unanimously approved a $51.3 million transmission-line agreement with Atlas Agro and Bonneville Power Administration on 2026-06-16; the line would ultimately power Atlas Agro's planned data center on Richland land and its fertilizer plant on Port of Benton land. The same article reiterates Atlas Agro's proposed $500 million data center on 275 acres of city-owned land, notes the city approved the option agreement in December 2025, and says Atlas Agro will have to source its own power while Richland facilitates distribution.

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-17. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.