Under Construction

Applied Digital Polaris Forge 2

North Dakota — Harwood , Cass County
Mega-Project
$3.0B
Investment
1
Sponsors

Sponsors & Partners

Project Timeline

Announced
2025-08-18
Construction Start
2025-09
Expected Completion
2027

Current canonical record

Campus contracted on more than 900 acres; latest disclosed lease covers 200 MW of critical IT load

Applied Digital describes Polaris Forge 2 near Harwood as an AI facility leased to Oracle. The company priced $2.15 billion of secured notes in March 2026 for development and construction, and North Dakota regulators approved a $110 million substation and high-voltage transmission project to serve the campus. Public descriptions use both 200 MW and 280 MW measures without consistently distinguishing critical IT load from total facility capacity, so this update does not overwrite the existing capacity fields.

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-19. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.