Project Timeline
Current canonical record
400 MW of critical IT load contracted at full buildout. The previously stored 342,000 square feet described one building, not the campus total.
Applied Digital announced on 2026-07-01 that Phase 1 of Building 2 at Polaris Forge 1 had reached Ready for Service, delivering 75 MW of operational AI capacity and bringing live campus capacity to 175 MW. The company also said the fully leased campus is contracted to deliver 400 MW of critical IT load at full buildout. Investment remains null because the cited source does not provide a total project investment figure.
Record provenance
This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-18. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.