Updated July 2026: the Essential Edition and its companion database are refreshedGet it on Amazon
Under Construction

Amazon Web Services (AWS) New Carlisle Campus

Indiana — New Carlisle, St. Joseph County
Mega-Project Northern Indiana
$11.0B
Investment
2.2 GW
Power Capacity
6.60M sq ft
Total Area
2
Sponsors

Sponsors & Partners

Project Timeline

Announced
2024-04-25
Construction Start
2024-09-30
Expected Completion
2034

Current canonical record

Campus features 33 data center 'shells,' each approximately 200,000 square feet, across two sites totaling 900 acres. 10-year build period.

Largest capital investment in Indiana state history. Expected to create at least 1,000 new jobs. IEDC committed data center sales tax exemptions for eligible capital investments over a 50-year term, plus up to $18.3 million in headcount-based tax credits, up to $5 million in training grants, up to $55 million in Hoosier Business Investment tax credits, and up to $20 million in redevelopment tax credits.

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-06-15. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.