Project Timeline

Announced
2025-10-30
Construction Start
2026

Current canonical record

575-acre campus at US-12 & Braun Road. Five buildings including three large data halls, generator facility, warehouse, and administrative office. Later 2026 financing and construction announcements describe the Oracle/Stargate campus as a US$16 billion project.

Sources in the Feb-Jun 2026 window report state air and wetland permits issued in January 2026, financing secured at $16 billion, and a June 1, 2026 groundbreaking/shovel ceremony for the 2.2 million sq ft campus. Planet Detroit reported the January permits allow destruction of about 9 acres of wetlands and installation of 15 diesel backup generators; Michigan Public reported the June 1 groundbreaking.

The Stargate campus in Saline Township is under construction. The 575-acre plan calls for approximately 2.2 million square feet across three large data halls and support buildings. The sponsors describe a closed-loop cooling system. The Michigan Public Service Commission conditionally approved DTE Electric contracts for a 1,383 MW load, with cost and emergency-curtailment protections for other customers.

The project amount is not the tax-abatement basis

Three figures describe different things and should not be combined:

FigureMeaning
$16 billionProject financing announced by Related Digital in April 2026
$43.098 billionReal- and personal-property investment claimed in Oracle America Cloud Services’ May 19, 2026 IFEC filing
$4.811 billionInvestment stated on the Form 1012 attached as Exhibit D to the October 2025 consent judgment

On July 14, 2026, the township board approved the Industrial Facilities Exemption Certificate at the original approximately $4.8 billion basis presented with the settlement rather than Oracle’s later $43.1 billion filing basis. A contemporaneous observer reported the vote as unanimous; the official minutes and adopted resolution were not yet available when this profile was updated. State Tax Commission review and the legal effect of the differing applications remain unresolved.

Timeline

DateEvent
September 10, 2025Township board rejected rezoning 4–1
October 15, 2025Consent judgment entered with IFEC terms and Exhibit D
October 30, 2025OpenAI, Oracle, and Michigan announced the Stargate campus
December 18, 2025MPSC conditionally approved DTE’s special contracts for 1,383 MW
April 24, 2026Related Digital announced $16 billion in financing
June 1, 2026Sponsors held a construction celebration and groundbreaking event
July 14, 2026Township board approved the IFEC at the original approximately $4.8 billion basis

Sources

Record provenance

This page is generated from the reviewed project database snapshot. The record was last reviewed on 2026-07-19. Blank fields mean the value was not publicly disclosed or could not be reconciled safely; they do not mean zero.